After I add additional flexible H2 production capacity, the merit order does not update automatically.
Step 1:
Step 2:
I need to refresh the page to see the installed 5 GW:
The H2 supply and demand balance does respond to the setting of this slider, so I think this is more a cosmetic problem, than a problem with the calculation not updating after the additional capacity is installed.
Is see that this problem also occurs in the district heating merit order sections. Perhaps other merit orders as well (how many more do we have)?
This problem doesn't occur in the electricity storage merit order where the merit order is 'refreshed' (calculated) when you got to > Merit order:
Whereas if you go to merit order section in hydrogen or district heating, the merit order is not 'refreshed' and will only refresh if you take an action that induces a recalculation (such as setting a slider or refreshing page). Therefore, there's this 'delay' in updating the merit order as depicted by Alex.
After I add additional flexible H2 production capacity, the merit order does not update automatically.
Step 1:
Step 2:
I need to refresh the page to see the installed 5 GW:
The H2 supply and demand balance does respond to the setting of this slider, so I think this is more a cosmetic problem, than a problem with the calculation not updating after the additional capacity is installed.
Notifying @kaskranenburg and @kndehaan
Re-assign as needed
The text was updated successfully, but these errors were encountered: