Parallelization is achieved by having multiple child processes running scenarios.

Customizable work assignment

Cucumber exposes customization of worker assignment via setParallelCanAssign. This can be used to prevent specific test cases from running at the same time.

The coordinator doesn't reorder work as it skips un-assignable tests. Also, it always returns to the beginning of the unprocessed list when attempting to make assignments to an idle worker.

Custom work assignment prioritizes your definition of assignable work over efficiency. The exception to this rule is if all remaining work is un-assignable, such that all workers are idle. In this case Cucumber assigns the next test to the first worker before continuing to utilize the handler to determine assignable work. Workers become idle after checking all remaining test cases against the handler. Assignment is attempted on all idle workers when a busy worker becomes ready.

Coordinator

  • load all features, generate test cases
  • broadcast test-run-started
  • create workers and for each worker
    • send an initialize command
    • when a worker outputs a ready command
      • if there are no more test cases, send a finalize command
      • identify the next processable test case (the next test by default)
      • when there are no processable test cases all idle workers remain idle
      • send a run command with the test case to an idle worker
      • repeat if there are still idle workers
    • if all workers become idle and there are more tests, process the next test case
    • when a worker outputs an event command, broadcast the event to the formatters, and on test-case-finished update the overall result
  • when all workers have exited, broadcast test-run-finished

Worker

  • when receiving the initialize command
    • load the support code and runs BeforeAll hooks
    • output the ready command
  • when receiving a run command
    • run the given testCase, outputting event commands
    • output the ready command
  • when receiving the finalize command
    • run the AfterAll hooks